Capitol Avenue Outfall
Bismarck, North Dakota
Project Details:
Urban storm water runoff from intense rainstorms has caused serious erosion along the Capitol
Avenue Outfall channel since development began in the 1970s. This erosion resulted in significant
damages to the channel and also exposed an adjacent 12-inch vitrified clay pipe sanitary sewer.
Early attempts to protect the sanitary sewer with riprap failed when the rock washed downstream
during subsequent rainstorms. The erosion extended from the outfall to the confluence with Hay
Creek (approximately 1,600 feet) and ranged from 10 feet wide and several feet deep to nearly 20
feet wide and over 12 feet deep.
The city of Bismarck, Bismarck Parks and Recreation District, and the Burleigh County Water
Resource District received an EPA Section 319 Grant for completing a water quality and quantity
assessment of the Hay Creek Watershed. This grant also provided assistance to develop and construct
Best Management Practices to address existing water quality issues and concerns. Houston
Engineering assisted the city of Bismarck in identifying an acceptable and economical solution for
the Capitol Avenue Outfall by completing an alternatives analysis, and then preparing the final
plans, specifications, and bid documents for the selected alternative.
Houston Engineering prepared a detailed alternative analysis for reconstructing the Capitol Avenue
Outfall, which defined the problems, project goals, alternative solutions, and included a value
engineering approach. The selected alternative defined multiple structural measures designed for
the 100-year flood peak including:
- 17-foot vertical cast in-place drop structure
- 450 lineal feet of 96-inch reinforced concrete pipe
- 120 lineal feet of a 10-foot rise by 12-foot span reinforced concrete box culvert
with energy dissipation blocks
- Rock riprap stilling basin
- 1,200 lineal feet of reconstructed channel that included an armored low flow section
and a designed floodplain
In addition, Houston prepared plans, specifications, and cost estimates for a 2.2 acre wetland
treatment system constructed to improve the water quality within Hay Creek. The wetland system will
reduce the inflow of sediments to the Creek, reduce peak discharges, and will also provide wildlife
habitat and aesthetics for those enjoying the adjacent walking trail.
Project Benefits:
- Aesthetically pleasing construction design that used a combination of traditional and
nontraditional methods
- Prevention of future erosion along the outfall
- Measurable reduction of sedimentation into Hay Creek
- Significant improvement in the quality of the discharge waters
Project Award:
2004 Engineering Excellence Honor Award, Category G
(Water Resources) from the ACEC North Dakota
|